Case Studies
Company |
C Butt Ltd |
Location |
Magna Park, Lutterworth |
Project Description |
Warehouse Lighting |
Scope of work |
Supply and fit warehouse lighting to include a new overhead Busbar system, three-phase distribution boards, Low Bay light fittings and Twin Spot Emergency Lighting Install power supplies within the warehouse for heaters, security cameras & alarms, battery charging area and general use sockets |
Special Features |
Worked with manufacturer to produce lighting scheme for the client and their landlord’s approval that would fit within the client’s available budget. Agreed a tight project timeline with the client to fit with other services being installed during the programme and achieved the milestones set out |
Company |
Ricardo MTC |
Location |
Midland Technical Centre – Leamington Spa |
Project Description |
Buildings One & Two |
Scope of work |
Building One was a single storey office refurbishment for one hundred desks involving a new suspended ceiling, a Cat2 lighting scheme, new three-phase distribution boards, Cat5e structured cabling and small power circuits. Building Two was a two-storey refurbishment involving structured cabling, 300 floor boxes supplying three Cat5e network connections and 13amp power, new three phase distribution boards and a new communications room complete with 19` cabinet suite Installation of new campus wide fibre optic connectivity Installation of multicore cross-site voice cabling Main reception area refurbishment including structured cabling, small power and an aesthetic lighting scheme Workshop/Shop Floor refurbishment including lighting, three phase power and machine moves |
Special Features |
Benefit from occupancy control lighting system identified by J&B and approved by the client. Campus/Car Park street lighting installed incorporating civil works and reinstatement of the landscape. Provision of ceiling grids and carpets incorporated into J&B remit to provide a turnkey solution |
Company |
Steel Construction Ltd |
Location |
Coventry |
Project Description |
Electrical refit to Shop Floor |
Scope of work |
Supply and fit new three phase panel board Supply and fit new three phase sub distribution boards Supply and fit low bay light fittings and emergency lighting Supply and fit 415V, 240V & 11OV supplies for various machines and general use |
Special Features |
Incorporated several variations and new instructions from the client into the original project timescales |
Company |
Nomenca |
Location |
Birmingham International Station |
Project Description |
Lighting & Distribution Upgrade |
Scope of work |
Replace lighting on platforms and concourse level Replace distribution boards throughout Replace sub-main cables throughout |
Special Features |
Kept lighting on to all areas throughout the project. Worked unsociable hours to meet project schedules |
Company |
Barsan Global Logistics |
Location |
Prologis Park, Coventry |
Project Description |
Warehouse Lighting |
Scope of work |
Supply and fit warehouse lighting to include three-phase distribution, fluorescent light fittings and Twin Spot Emergency lighting |
Special Features |
Occupancy controlled lighting with natural daylight override facility |
Company |
Dunlop Aerospace (Fluid Dynamics) |
Location |
Coventry |
Project Description |
Repair/replace fire damaged electrical services |
Scope of work |
Attend site immediately and assess damage caused by a fire Effect immediate repairs to enable some areas of the plant to return to production Strip out and replace damaged electrical installation |
Special Features |
J&B were able to attend site the day after the fire and start work immediately to get the plant running again in the shortest possible time |
Company |
Midland Steel Structures Ltd |
Location |
Coventry |
Project Description |
New Building |
Scope of work |
Workshop: Supply and fit new three phase panel board Supply and fit new three phase sub distribution boards Supply and fit low bay light fittings and emergency lighting Supply and fit 415V, 240V & 11OV supplies for various machines and general use Supply and fit fans in the roof Office Area: Supply and fit office and general lighting Supply and fit small power requirements GeneralL: Supply and fit external lighting Supply and fit fire alarm system |
Special Features |
External lighting fitted with daylight sensors and timer facility |
Company |
Optilan UK Ltd |
Location |
Coventry |
Project Description |
Electrical & Network Cabling installation to new offices |
Scope of work |
Supply and fit new three phase panel board Supply and fit new three phase sub distribution boards Supply and fit Cat2 office lighting Supply and fit high level warehouse lighting Supply and fit small power requirements Installation of Cat6 structured cabling system |
Special Features |
Worked with other trades on site to achieve programmed milestones and the clients moving in date |
Company |
Briggs & Forrester MEP Ltd |
Location |
University of Birmingham – Masons Hall |
Project Description |
Electrical installation to new student accommodation blocks |
Scope of work |
Full electrical installation to over one hundred, six bed and kitchen apartments Sub main cabling to each flat Landlords cabling to common areas and stairwells Street Lighting to campus |
Special Features |
Flexible approach to changing deadlines and project milestones over twelve months |